January: Funding recieved and raw materials ordered
February: Last Phase of Analysis is completed
March 3: Milling of Materials Begins
March 10: All four curved sections milled, 1 curved section tapped for radiator cap assembly, 1 square channel milled for electrode placement
March 14: Materials Dropped Off at Welder
March 17: Quote Recieved
March 24: Welded Materials Ready to Pick Up
April: Lots of construction
April 17: It's alive! It's aliiiiiive!
April 20-22: Team is in Washington DC for the EPA P3 Expo